UAF 48 Volt Battery System Maintenance (AHRB & Duckering)
Scheduled Maintenance Report for UAA IT Services
Completed
The scheduled maintenance has been completed.
Posted Apr 13, 2023 - 08:37 AKDT
Update
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 22, 2022 - 11:15 AKST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 22, 2022 - 11:00 AKST
Update
Maintenance will begin as scheduled in 60 minutes.
Posted Dec 22, 2022 - 10:15 AKST
Scheduled
UAF will be performing battery maintenance on the 48 volt backup battery systems in AHRB and Duckering buildings. Electrical circuits will be shut down via the transfer switches prior to battery bank maintenance. Services will be restored after maintenance is completed.

Legacy circuits that traverse campus may be impacted by this maintenance window. It is not expected to impact primary network systems.
Posted Dec 21, 2022 - 13:00 AKST